Job
CCH43524 · Superior Construction - SR 140 over Big Blue River
Active- Job #
- CCH43524
- Customer
- Superior Construction
- Channel
- Highway
- Project
- SR 140 over Big Blue River
- Linked bid
- -
- PO
- -
- Coating mix
- 47% black / 53% epoxy
- Est vs released
- 148.9 tons / 0.0 tons
- First requested
- 10/09/26
- Last requested
- 01/15/27
- Releases open
- 10
- Releases shipped
- 0
- Shipped tons
- 0.0 tons
- Remaining tons
- 140.5 tons
- Last activity
- 10/17/26
- Closed
- –
- Invoiced to date
- $0
- Open AR
- $0
- QuickBooks
- Open in QuickBooks
- Last modified
- T. Hannon · Oct 19, 10:00 AM ET
Total: 10
| BED / 1 | Pier 2 footing | Listed | 11/24/26 | 19.6 tons | 19.6 tons |
| CUI / 2 | Pier 2 footing | Listed | 10/09/26 | 17.2 tons | 17.2 tons |
| EKM / 3 | Pier 2 footing | Listed | 11/15/26 | 7.9 tons | 7.9 tons |
| GAR / 4 | Pier 2 footing | Listed | 01/12/27 | 21.1 tons | 21.1 tons |
| HQW / 5 | Pier 2 footing | Listed | 10/30/26 | 3.3 tons | 3.3 tons |
| JGA / 6 | Pier 2 footing | Listed | 12/26/26 | 9.2 tons | 9.2 tons |
| KWF / 7 | Pier 2 footing | Listed | 10/11/26 | 17.5 tons | 17.5 tons |
| MMK / 8 | Pier 2 footing | Listed | 12/21/26 | 4.3 tons | 4.3 tons |
| OCO / 9 | Pier 2 footing | Listed | 12/08/26 | 21.1 tons | 21.1 tons |
| PST / 10 | Pier 2 footing | Listed | 01/15/27 | 19.4 tons | 19.4 tons |