CCH43521 · HIS Constructors - Parkview Health
Active- Job #
- CCH43521
- Customer
- HIS Constructors
- Channel
- Highway
- Project
- Parkview Health
- Linked bid
- -
- PO
- -
- Coating mix
- 0% black / 100% epoxy
- Est vs released
- 169.0 tons / 159.5 tons
- First requested
- 10/05/26
- Last requested
- 01/11/27
- Releases open
- 0
- Releases shipped
- 10
- Shipped tons
- 159.5 tons
- Remaining tons
- 0.0 tons
- Last activity
- 10/12/26
- Closed
- –
- Invoiced to date
- $0
- Open AR
- $0
- QuickBooks
- Open in QuickBooks
- Last modified
- M. Reyes · Oct 17, 10:00 AM ET
Total: 10
| BBD / 1 | Foundation walls | Shipped | 10/05/26 | 20.8 tons | 0.0 tons |
| CRH / 2 | Foundation walls | Shipped | 12/17/26 | 22.9 tons | 0.0 tons |
| EHM / 3 | Foundation walls | Shipped | 10/07/26 | 17.6 tons | 0.0 tons |
| FXR / 4 | Foundation walls | Shipped | 12/30/26 | 5.6 tons | 0.0 tons |
| HNV / 5 | Foundation walls | Shipped | 10/14/26 | 17.6 tons | 0.0 tons |
| JDA / 6 | Foundation walls | Shipped | 11/18/26 | 21.5 tons | 0.0 tons |
| KTF / 7 | Foundation walls | Shipped | 01/11/27 | 17.7 tons | 0.0 tons |
| MJJ / 8 | Foundation walls | Shipped | 12/10/26 | 15.6 tons | 0.0 tons |
| NZO / 9 | Foundation walls | Shipped | 12/25/26 | 11.1 tons | 0.0 tons |
| PPT / 10 | Foundation walls | Shipped | 10/13/26 | 9.2 tons | 0.0 tons |